On February 12, 2026, the Treasury Department (Treasury) and the Internal Revenue Service (IRS) issued Notice 2026-15 (the Notice). The Notice describes certain rules to be included in forthcoming proposed regulations addressing the prohibited foreign entity (PFE) material assistance requirements for purposes of Sections 48E (CEITC), 45Y (CEPTC), and 45X (advanced manufacturing credit), and safe harbor tables for determining the applicable material assistance cost ratio (MACR). The PFE regime (also known as FEOC, or foreign entity of concern) was enacted by the One Big Beautiful Bill Act (OBBBA).
Executive Summary
The Notice provides both general rules and safe harbors for determining the MACR, which must exceed the Applicable Threshold Percentage (defined below). Because compliance with the general rules could be difficult, and because the safe harbors are available for the most common projects (including solar, wind, and battery projects), we expect the safe harbors to be widely used.
The Notice outlines a five-step process for determining the MACR for the CEITC and CEPTC (i.e., Clean Electricity MACR) for a qualified facility or energy storage technology (EST).
A similar process applies for determining the MACR for the advanced manufacturing credit.
Unfortunately, the Notice does not address the other two FEOC rules — i.e., the rules for determining whether a taxpayer is a PFE and whether contracts applicable to a qualified facility or EST confer effective control.
Definitions
The Notice and Section 7701 rely on several key definitions that are fundamental to understanding the material assistance restrictions.
OBBBA Material Assistance Requirements
Under the OBBBA, a qualified facility or EST that begins construction after the end of 2025 (or, in the case of the advanced manufacturing credit, in taxable years beginning after July 4, 2025, if an eligible component is used in a product sold before January 1, 2027) is ineligible for the CEITC, CEPTC, and advanced manufacturing credit if it receives material assistance from a PFE, which means that the qualified facility, EST, or eligible component, as applicable, has a MACR that is less than the Applicable Threshold Percentage.
The OBBBA required the Secretary of the Treasury to issue safe harbor tables to simplify this determination no later than December 31, 2026. The Notice provides two interim safe harbors that allow taxpayers to rely on tables in previously issued domestic content guidance: the Identification Safe Harbor and the Cost Percentage Safe Harbor. The Identification Safe Harbor allows taxpayers to rely on such tables to identify the manufactured products and manufactured product components in a qualified facility or EST (or constituent materials, for purposes of the Eligible Component MACR). The Cost Percentage Safe Harbor allows taxpayers to rely on such tables to determine its direct costs (or direct material costs, for purposes of the Eligible Component MACR) by applying specified cost percentages assigned to each manufactured product and manufactured product component.
The Certification Safe Harbor allows taxpayers to rely on a certification for purposes of determining which manufactured products and manufactured product components are produced by a PFE (for the Clean Electricity MACR) or constituent materials are sourced from a PFE (for the Eligible Component MACR) and the portion of a taxpayer’s costs associated with each manufactured product component or constituent material.
Clean Electricity MACR
The calculation of the Clean Electricity MACR is done on a qualified facility-by-qualified facility and EST-by-EST basis as follows:
Identify MPs and MPCs
Taxpayers may use the Identification Safe Harbor to identify MPs and MPCs of a qualified facility or EST. The Identification Safe Harbor allows taxpayers to treat the MPs and MPCs listed in the applicable 2023-2025 Safe Harbor Table for each qualified facility or EST as the exclusive and exhaustive list of MPs and MPCs that are incorporated into the qualified facility or EST. For purposes of the Identification Safe Harbor, each of the following is disregarded: (i) any MP or MPC contained in a qualified facility or EST that is not listed in the applicable 2023-2025 Safe Harbor Table, (ii) any MP or MPC that is listed in the applicable 2023-2025 Safe Harbor Table but is not contained in a qualified facility or EST, (iii) any items classified as “Steel/Iron” in the applicable 2023-2025 Safe Harbor Table, and (iv) when applying the 80/20 rule for a repower, any used property that is part of a qualified facility.
Taxpayers that do not use the Identification Safe Harbor must identify each MP and MPC incorporated into the qualified facility or EST based on the actual items used in the construction or installation of the qualified facility or EST. The Notice states: “To identify MPs and MPCs, a taxpayer must identify the types of MPs and MPCs that are incorporated into the qualified facility or EST. A type of MP or MPC refers to a type of product or component that performs a unique, specified function within the qualified facility or EST.”
Track MPs and MPCs
Except as described below, each MP and MPC (and its characteristics) must be individually tracked to the specific qualified facility or EST into which it is incorporated. All taxpayers must track whether each MP or MPC was PFE Produced. Taxpayers not using the Cost Percentage Safe Harbor also must track the taxpayer’s direct costs of each MP and MPC.
Taxpayers may use the Certification Safe Harbor to determine which MPs and MPCs incorporated in a qualified facility or EST are PFE Produced. The Certification Safe Harbor permits a taxpayer to rely on written certifications from direct suppliers for purposes of determining whether MPs or MPCs are PFE Produced. Taxpayers that do not use the Certification Safe Harbor must determine whether each MP and MPC is PFE Produced, taking into account ownership, control, and status of the relevant producer under the specified foreign entity and foreign-influenced entity rules, which include complex attribution concepts.
The Notice provides a de minimis assignment rule that is an exception to the requirement to individually track MPs and MPCs of the same type. Under this rule, a taxpayer may choose how to assign MPs or MPCs of the same type to qualified facilities or ESTs if the aggregate direct costs of the MPs and MPCs assigned do not exceed 10% of the total direct costs of the qualified facility or EST.
The Notice also provides another exception from the tracking rule for certain ESTs that (i) are of the same type (based on a shared production line, method and capacity of energy storage, or any other reasonable method) (ii) have a maximum net output of less than 1MW (AC), and (iii) are placed in service during the same taxable year. A taxpayer may track the characteristics of each MP or MPC incorporated in such ESTs by calculating the average of direct costs of the MPs and MPCs of the same type incorporated in the ESTs (for taxpayers not relying on the Cost Percentage Safe Harbor) and calculating a percentage of MPs and MPCs that were mined, manufactured, or produced by a PFE and incorporated in the ESTs placed in service during a specified period. Detailed timing rules apply for this purpose.
Determine Direct Costs and PFE Direct Costs
A taxpayer that uses the Identification Safe Harbor may utilize the Cost Percentage Safe Harbor to determine direct costs and determine PFE Direct Costs, except with respect to qualified facilities that include a new unit or addition of capacity to an existing qualified facility that was placed in service before 2025. Under the Cost Percentage Safe Harbor described below, taxpayers may determine direct costs using the Assigned Cost Percentages of the MPs and MPCs set forth in the domestic content notices in lieu of actual direct costs. The total Direct Costs are equal to the sum of the Assigned Cost Percentages assigned to each MP and MPC in the applicable 2023-2025 Safe Harbor. The PFE Direct Costs are equal to the sum of the Assigned Cost Percentages for the MPCs that are PFE Produced and the Assigned Cost Percentage for Production for MPs that are PFE Produced.
Taxpayers that do not use the Cost Percentage Safe Harbor must determine the actual direct costs attributable to each MP and MPC incorporated in a qualified facility or EST. For MPs acquired by a taxpayer, the direct costs attributable to an MP include acquisition costs with respect to the MP. For MPs produced by a taxpayer, direct costs include the taxpayer’s material costs and direct labor costs, as defined in the Section 263A regulations.
For these purposes, if the taxpayer acquires a PFE Produced MP, but some or all of the MPCs included in the MP are not PFE Produced, then the taxpayer excludes from PFE Direct Costs the portion of the MP’s acquisition costs that are attributable to the MPCs that are not PFE Produced. If the taxpayer acquires an MP that is not PFE Produced, but some or all of the MPCs included in the MP are PFE Produced, then the taxpayer includes in PFE Direct Costs the portion of the MP’s acquisition costs that is attributable to the PFE Produced MPCs. If the taxpayer produces an MP that includes any acquired PFE Produced MPCs, then the taxpayer’s PFE Direct Costs include the acquisition costs of the PFE Produced MPCs.
The Notice provides that taxpayers that do not use the Cost Percentage Safe Harbor may use the Certification Safe Harbor to determine direct costs in whole or in part where a supplier has stated the total direct costs paid for the MP or MPC.
Eligible Component MACR
To calculate the Eligible Component MACR for an eligible component, a taxpayer must:
Identify Constituent Materials
Taxpayers may use the Identification Safe Harbor to identify types of Constituent Material only if the eligible component is specifically listed in the Notice. These listed components include inverters, solar modules, and battery packs/modules. The Identification Safe Harbor provides an exclusive and exhaustive list of Constituent Materials that is consistent with the MPCs listed in the applicable 2023-2025 Safe Harbor Tables. Accordingly, if a taxpayer manufactures one of these specified components and elects to use the Identification Safe Harbor, any materials not listed as an MPC can be disregarded.
Taxpayers that do not use the Identification Safe Harbor must identify each Constituent Material actually incorporated into the eligible component by reference to the component’s production or purchase records.
Track Constituent Materials
Except as described below, each Constituent Material must be tracked (and its relevant characteristics) to the eligible component into which it is incorporated.
All taxpayers must track whether each Constituent Material was PFE Produced. Taxpayers not using the Cost Percentage Safe Harbor also must track the taxpayer’s direct material costs attributable to each Constituent Material. Taxpayers may use the Certification Safe Harbor to determine whether Constituent Materials used to produce an eligible component are supplied by a PFE.
Unlike the Clean Electricity MACR, the Notice does not provide any de minimis assignment rule or aggregation rule for tracking Constituent Materials for purposes of the Eligible Component MACR.
Determine Direct Material Costs and PFE Direct Material Costs
Taxpayers that use the Identification Safe Harbor may utilize the Cost Percentage Safe Harbor to determine direct material costs and PFE Direct Material Costs by summing the assigned cost percentages for each Constituent Material listed in the applicable 2023–2025 Safe Harbor Tables, and by summing the assigned cost percentages for only those Constituent Materials that are supplied by a PFE.
Taxpayers that do not use the Cost Percentage Safe Harbor must determine the actual direct material costs attributable to each Constituent Material incorporated into the eligible component. Direct material costs include amounts paid or incurred by the taxpayer for materials that are incorporated into the eligible component or consumed in the production of the eligible component.
Certification Safe Harbor Requirements
The Notice provides that, for a certification to be relied upon under the Certification Safe Harbor, it must be obtained from the direct supplier of the relevant MP, MPC, eligible component, or Constituent Material and must be signed under penalties of perjury. The certification must include the supplier’s employer identification number (or comparable foreign tax identification number) and must state, as applicable, that the relevant MP, MPC, eligible component, or Constituent Material was not mined, produced, or manufactured by a PFE and that the supplier does not know (or have reason to know) that any prior supplier in the chain of production is a PFE, or must state the portion of direct costs or direct material costs attributable to MPs (for the CEITC and CEPTC) or Constituent Material (for the advanced manufacturing credit) that were not supplied by a PFE. The taxpayer must attach the certification to the return or forms for claiming the relevant credit (e.g., Form 3468 for the CEITC and Form 7211 for the CEPTC). A taxpayer may rely on a certification unless it knows or has reason to know that the certification is inaccurate.
Qualified Interconnection Property
For purposes of calculating the Clean Electricity MACR for a qualified facility that claims the CEITC, costs attributable to qualified interconnection property (QIP) are excluded from the Clean Electricity MACR. If a taxpayer calculates a separate Clean Electricity MACR for the QIP that does not satisfy the Applicable Threshold Percentage that applies to the qualified facility, or if a taxpayer is unable to calculate a Clean Electricity MACR for the QIP, then the taxpayer is not precluded from claiming the CEITC for the qualified facility. Costs attributable to QIP are eligible for the CEITC if both the Clean Electricity MACR for the QIP and the Clean Electricity MACR for the applicable qualified facility satisfy the Applicable Threshold Percentage.
Reliance
Taxpayers may rely on the rules described in the Notice for (i) any qualified facility or EST the construction of which begins before the date that is 60 days after the date of publication of the forthcoming proposed regulations in the Federal Register and (ii) eligible components sold in taxable years beginning on or before the date that is 60 days after the date of publication of the forthcoming proposed regulations in the Federal Register.
Taxpayers may rely on the safe harbors in the Notice to calculate the applicable MACR for (i) any qualified facility or EST the construction of which begins before the date that is 60 days after the date of publication of forthcoming safe harbor tables under Section 7701(a)(52)(D)(iii)(I) or (ii) eligible components sold in taxable years beginning on or before the date that is 60 days after date of publication of forthcoming safe harbor tables under Section 7701(a)(52)(D)(iii)(I).
Foreign-Influenced Entity: Licensing Agreements
The Notice describes rules that the Treasury Department and the IRS expect to include in the forthcoming proposed regulations for determining the application of certain PFE restrictions.
Notably, the Notice clarifies that, for purposes of the FIE definition in Section 7701, an SFE is determined to exercise effective control as a result of any contract, agreement, or other arrangement that fulfills one of the listed qualities in Section 7701(a)(51)(D)(ii)(III)(aa)(AA) through (GG), including a licensing agreement for the provision of intellectual property with respect to a qualified facility entered into or modified after July 4, 2025.
Request for Comments
The Notice includes a request for comments by March 30, 2026 with respect to whether further guidance is needed to clarify how to determine total direct costs of a qualified facility or EST, anti-circumvention rules, and what substantiation and documentation should be required to support compliance with anti-circumvention rules, such as to demonstrate the beginning of construction has occurred for purposes of the PFE and material assistance rules.
Conclusion
It is perhaps unfortunate for the CEITC and CEPTC that Treasury and the IRS prioritized the material assistance guidance. Given that many sponsors used beginning of construction strategies to ensure significant portions of their pipelines would not be subject to the material assistance requirements, the need for guidance on the PFE and effective control rules is even more pressing.
However, the Notice provides welcome relief. Many feared the material assistance requirements were a poison pill for the renewables industry. Fortunately, Notice 2026-15 sets forth rules, including safe harbors, that incorporate familiar principles from the domestic content guidance. The Notice will be very helpful for projects eligible for the safe harbors, including solar, wind, and battery projects and domestic manufacturers of inverters, solar modules, and battery packs/modules. On the other hand, supply chains must evolve to enable manufactured products to satisfy increasingly stringent requirements. In addition, the path to satisfying the material assistance requirements will be more difficult for projects and manufacturers that cannot take advantage of the safe harbors.
We have been working with sponsors on procurement strategies and manufacturers on their supply chain strategies, and we will be incorporating the guidance from Notice 2026-15 into these. Please feel free to reach out to us if you would like to discuss Notice 2026-15 or the PFE rules more generally.e. Please feel free to reach out to us if you would like to discuss Notice 2026-15 or the PFE rules more generally.
Gibson Oddderstol also contributed to this article. He is not licensed to practice law in any jurisdiction; bar admission pending.
This just in
Speaking Engagements
Healthcare Securities Class Actions, SEC Enforcement & Emerging Capital Markets Risks
September 2, 2026
Firm Events
Cocktails and Networking During MEDevice Boston
August 26, 2026 | 6:00 PM – 8:00 PM ET
Lifted Restaurant
450 Summer St, Boston, MA 02210
Sponsored Events
San Francisco Renewable Energy Drinks: End of Summer Party
August 26, 2026 | 5:00 PM – 8:00 PM PT
Spark Social SF
601 Mission Bay Blvd North, San Francisco, CA 94158-2472
Speaking Engagements
The 2026 Multifamily Maturity Cliff: Reading the $162 Billion Refinancing Wave and the Engagements It Will Generate
August 26, 2026 | 1:00 PM – 3:10 PM ET
Webinar